CONSTRUCTION OF FOUR BACHELOR ACCOMMODATION BLOCK, EACH COMPRISING OF FOUR SELF-CONTAINED UNIT
CONSTRUCTION OF FOUR BACHELOR ACCOMMODATION BLOCK, EACH COMPRISING OF FOUR SELF-CONTAINED UNIT
Country: Ghana
Name of Employer: Interbeton BV
- Employer address : O. Box 9101 KIA, Accra Ghana
- Nature of project and special features relevant to the contract of which Applicant
wishes to prequalify:
General construction work, including installation of air conditioners, etc.
- Contract role
Prime contractor
- Amount of the total contract
₵1,240,725,600.00
- Equivalent Amount US$
Total contract: $136,343,47
- Date of award /completion October 2005/April 2006
- Contract was completed first month behind schedule, because of introduction of new areas of construction of external drains and the use of T&C instead of originally propose plywood ceiling.
- Contract was completed US$28,491.69 over original contract amount.
- Special contractual requirements, including monthly/annual production/operational rates of the key project activities. None
- Indicate the approximate percent of total contract value (and US$ amount)of work undertaken by sub contract, if any, and the number of work. None